1.) Public
Hearing – Continuation of Proposed 2008 Operating,
Capital Reserve, Liquid Fuels, Water and Sewer Budgets (Review and Discussion).
Chairman
Paulus opened the Public Hearing relative to the proposed
2008 Budgets. In attendance at the meeting was the Township
Engineer to review with the Board the proposed 2008 Sewer
and Water Budgets. In that regard, the Township Engineer
began a review with the Board of the proposed 2008 Water
Budget. Mr. Hay noted that the Beginning Operating Reserve
proposed at $900,000 includes the Revenues from the Capital
Program for Water System Improvements, which had reverted
back to the Water Account as a result of non-expenditure
over a three year period. As Council was aware, in accordance
with the Township Charter if funds are not expended for a
three year period, they revert back to the fund from which
they were appropriated. The Township Engineer reviewed with
the Board the proposed Revenue portion of the Water Budget
and Council made no revisions to same. With respect to the
Expenditure portion of the Budget, the Township Engineer
reviewed same with the Board and no revisions were made to
the Expenditures as set forth. The Township Engineer advised
the Board that the usage rate for customers has been reduced
from $5.10 to $2.75 in the proposed Budget and that the minimum
usage has been set at 7,000 gallons per quarter. Mr. Hay
noted that previously the minimum usage had been 11,000 gallons.
At this
point in the meeting, the Township Engineer reviewed with
the Board the proposed Sewer Budget for the year 2008. The
Township Engineer advised that this proposed Budget sets
forth a flat rate for usage of $5.00 per 1,000 gallons of
usage. Additionally, the Township Engineer noted that a minimum
has been set at $35.00 representing 7,000 gallons usage.
The Township Engineer advised the Board that some of the
Township’s biggest users over the last few years have
gone away. He cited the Sure Fit facility as well as the
Qualex facility. As Council is aware, Sure Fit is not in
existence and Qualex has reduced their usage. Basically,
the Township Engineer advised that we don’t have the
flows but still have the expenses. With respect to the current
rates as they compare with the proposed $5.00 flat rate,
the Township Engineer noted that the Allentown rate for Usage
and Capital Costs currently is $4.02. The rate for Bethlehem
users for Usage and Capital Costs is $3.55 and the rate for
Catasauqua users including Usage and Capital Costs is $4.29.
There was a discussion with respect to the minimum and Councilman
Atkinson noted that the minimum is really a minimum charge
which is necessary for maintenance of the sewer system. There
was also a discussion regarding the fact that the Township
does have excess capacity in both Bethlehem and the Catasauqua
sewer plants. As Council is aware, Mr. Hay noted that some
of the Catasauqua usage has been sold to Hanover Township,
Northampton County, and that the new shopping center would
utilize Catasauqua sewer. With respect to Bethlehem, the
Township Engineer indicated that we have 250,000 gallons
per day capacity and average approximately 125,000 gallons
per day. Mr. Hay did note that the law states that you must
cover 80% of your flows. Mr. Hay noted that he is aware that
Bethlehem Township is in current need of sewer capacity but
that he would like to check the IMA with the City of Bethlehem
before making any recommendations to the Board regarding
sale of the additional capacity. After all the discussions
regarding the proposed Sewer Budget, the Budget as stated
remained unchanged.
At this
point in the meeting, Councilman Paulus closed the Public
Hearing relative to the proposed 2008 Budgets. It was noted
that the next meeting would be held on Monday, November 12,
2007 at 7:00 P.M. for review of the Highway Budget set forth
in the General Fund as well as the Fire Department and Emergency
Management Budgets set forth in the General Fund.