Chairman
Paulus opened the Public Hearing relative to the Proposed
Five Year Capital Program. The Township Manager proceeded
to provide the Board with an overview of the contents of
the program beginning with the program for Miscellaneous
Stormwater Projects. The Township Manager advised that the
program sets forth a $100,000 a year appropriation for the
five-year period. It was further noted that the monies in
escrow would be sufficient should the Township determine
to contribute monies toward the work proposed in the Allendale
swale area as a result of the proposed shopping center project
on Airport Road.
With respect
to the program for Traffic Congestion Improvements, the Township
Manager advised that it is anticipated to have the installation
of a signal light at the Race Street/Willowbrook Road intersection
hopefully before the end of 2006. Assuming the cost thereof
in the area of $50,000 to $100,000, the Township Manager
advised that in the year 2007 the program shows a $100,000
appropriation for that year to bring the monies in escrow
balance in line with its current balance.
With respect
to the program titled Future Road Construction Projects,
the Township Manager advised that a $750,000 appropriation
is shown for the year 2007 with a $500,000 appropriation
each year thereafter for the five- year period. The Township
Manager noted that the program titled Catastrophe Fund shows
a $75,000 appropriation in the year 2007 with a $25,000 appropriation
each year thereafter through 2011. The Township Manager noted
that the $75,000 appropriation in the year 2007 is set forth
to help recover monies which the Catastrophe Fund paid out
in the year 2006 as a result of the fire at the Township
garage.
The program
titled Canal Project/DCED Grant shows a $160,000 appropriation
in the year 2007 and a $150,000 appropriation each year for
the years 2008 through 2011. The $10,000 additional shown
in the year 2007 takes into account the possibility of a
DCED Grant in the year 2007. The program titled Pump Station
Upgrades and Sewer Line Upgrades shows a $150,000 appropriation
each year for the years 2007 through 2011. The program titled
Water System Improvements/Allendale Area shows a $50,000
appropriation across the board for the five- year period.
The program titled Fire Apparatus/Squad Truck does not show
an appropriation since it is anticipated that the monies
held in escrow will be utilized in the year 2006 for full
payment of the Squad Truck.
The Board
entered into discussion at this point in the meeting. It
was noted that some of the anticipated expenditures with
respect to the Capital Program have not come to pass, i.e.
the Canal System being revamped and the Lock being restored.
However, Council did discuss the Hanover Township Home Rule
Charter requirements for expenditure of funds and that a
meeting with the Township Solicitor in the future may be
necessary to review the situation. There was a discussion
with respect to amendments to the Home Rule Charter. There
was discussion with respect to the Township’s Business
Privilege Tax rate. The Township Manager was directed to
check with the Tax Collector to determine exactly how that
works.
It was
noted that the Township Engineer is looking into the possibility
of a flat rate for all sewer customers. There was also discussion
with respect to the fact that the Township Engineer is researching
potential discrepancies between Bethlehem consumptions and
Township sewer bills to determine if there could be a glitch
in the Township’s computer system. The Township Manager
was directed to determine the time frame for the signal light
installation at Race Street and Willowbrook Road. Additionally,
the Township Manager was asked to check with the Township
Engineer regarding the status of the Canal Project work requiring
approval from the Army Corps of Engineers.
In conclusion
of the Public Hearing, it was noted that additional hearings
were not necessary and accordingly all future hearings would
be canceled. The adoption of the Five Year Capital Program
would occur in an upcoming meeting by way of Resolution and
amendments to the program would be made by the Township Manager
to accurately reflect balances in the accounts and funding
of the accounts.